Miami’s Ghost Trail: A Decade After Approval, the Ludlam Trail Is Still Mostly Fences
Miami-Dade has spent tens of millions on a nearly six-mile path through the west side of the county, and finally hired a designer this summer. Neighbors are still waiting for a single continuous mile they can walk.

Drive along Southwest 69th Avenue in west Miami-Dade and you’ll see it: a long, narrow strip of land running behind backyards and strip malls, mostly hidden behind chain-link fence. It’s the old Florida East Coast Railway corridor, and for years it has been the future site of the Ludlam Trail, a 5.6-mile path for walkers, runners and cyclists.
It was supposed to be one of the county’s signature green projects, a cousin to the Underline in Brickell. Instead, it has become a case study in how slowly big public projects move in South Florida.
Years of promises
Miami-Dade approved the Ludlam Trail plan in 2015. In 2018, county commissioners approved buying the rail property for about $24.6 million. A groundbreaking ceremony followed in 2021. Advocates say the county has spent roughly $42 million on the project so far.
Yet most of the corridor remains closed. In 2024, the county’s parks department said construction was expected to start in fall 2026. That hasn’t happened. A nearly two-year search for a design firm dragged on without a signed contract until July, when county commissioners unanimously approved a $9.5 million contract to design the trail. Mayor Daniella Levine Cava called the vote a “significant milestone.”
A significant milestone.Miami-Dade Mayor Daniella Levine Cava, on the trail’s design contract
What’s slowing it down
Part of the problem is what’s in the ground. The corridor carried freight trains for decades, and sections are fenced off because of soil contamination. Several brownfield sites have to be cleaned up or capped before anyone can build a path on top of them, adding time and cost.
The trail also has to cross some of the busiest roads in the county. The Florida Department of Transportation has agreed to design and build pedestrian bridges over Flagler Street, Southwest Eighth Street and Bird Road. A fourth bridge, over Coral Way, is being built by a private developer under an agreement with the county, connected to a new senior housing project next to the corridor.
And money remains an open question. The county’s current budget sets aside about $11.7 million for construction and land acquisition and $750,000 for planning and design, but officials have not announced a total cost or a full plan to pay for it. The city of Miami is now considering whether to fund its share of the project, Miami Today reported this week.
Neighbors want a date
A small section south of Bird Road is already open, built as part of private development along the corridor. For everyone else, the trail is still a promise. Advocates have revived a group called Friends of the Ludlam Trail and are pressing county staff for firm dates and dollar figures. Critics also worry about developer “nodes” that replace pieces of the public trail with private construction.
More from Amerigo
Latest stories
Music · Italian American Heritage
Dino From Steubenville: How Dean Martin Made Being Italian Look Effortless
The barber’s son from an Ohio steel town boxed as “Kid Crochet,” dealt cards in a back-room casino and sang as “Dino Martini” before becoming the coolest man in America. Unlike Sinatra, he never stopped singing in Italian.

World · Vatican
Pope Leo XIV to Have Lung Surgery After Doctors Find Early-Stage Nodule
The 71-year-old pope announced the news himself from St. Peter’s Square, saying the nodule was caught early and that he had decided to have it removed. The Vatican expects about a week of recovery.

Music · Italian American Heritage
Frank Sinatra and the Price of a Name
Born in a Hoboken tenement to a Sicilian boxer and a Ligurian political boss, Sinatra turned down the chance to become “Frankie Satin” and became the most famous Italian American of the century, with all the pride and baggage that came with it.